Lekki Pearl November Development Update

SITE UPDATE


1. CONSTRUCTION OF CARCASS AT 100% CONSTRUCTION STAGE; ROOFING OF SAME COMPLETED

The construction of the carcass of the first set of 5 units of Terrace houses has reached completion stage. As shown in the attached picture(s), the roofing of same has been completely done. With these stages completed, work will commence on other housing units.

Side view of completed terrace

 

Roofing of first set of Terrace completed

 

2. MEP WORKS AND SLAB REINFORCEMENT CONTINUE ON BLOCK 2

The MEP works on the second block of housing unit to be assembled and casted has reached completion stage while the slab reinforcement has reached completion stage. With this, the block is ready for assembling of the form works and casting.

Aerial view of the completed slab

 

Another view of the completed slab

 

3. SCREEDING OF INTERIOR PARTS COMMENCES

The screeding of the walls in preparation of the wall final finishing has commenced in the first unit of the completed terrace block. This is also in preparation towards the open house event which has now been scheduled to take place before the end of November. Further information about this will be forwarded within the shortest time frame possible.

SITE UPDATE IN PHOTOGRAPHS

 

 

OTHER NEWS

4. SAND FILLING OF THE SITE CONTINUES

The sand filling of other parts of the project site is still in progress and gradually reaching completion stage.

Continuation of the sand filling process