Lekki Pearl December Update

SITE UPDATE

1. CONSTRUCTION OF CARCASS AT 100% CONSTRUCTION STAGE; INTERNAL FINISHINGS COMMENCE

The construction of the carcass of the first set of 5 units of Terrace houses has reached completion stage. As shown in the attached picture(s), the roofing of same has been completely done just as stated in our previous newsletter. With these stages completed, work will commence on other housing units.

Also, the internal works on the first unit which would serve as the show house has commenced with the follow details being attended to and is expected to be completed in another two weeks -

  • Tiling: The wall and floor tiles are at 80% completion stage with the tiling of the Master’s toilet/bathroom currently ongoing.
  • Sanitary Wares: The sanitary units; i.e. the bath tubs and water closets with cistern tanks have been installed.
  • Terrace Rails/Aluminum duct cover: The external terrace rails have been fixed and the Aluminum duct cover has also been fixed.
  • Internal Stair Rails: These have also been fixed and the wooden finishing on same fully completed
  • Internal Door Frames Setting: In progress
  • Kitchen Fittings: The installations of the kitchen cabinets are in progress while other kitchen fittings will follow suit upon completion of the kitchen cabinets.
  • Screeding of external walls/Installation of Inverter: The screeding of the external walls is in progress and same is expected to be completed in a matter of days.

 

 
  Wooden finishing on staircase rails Terrace Rails fixed
 
  Entrance Door Screeding of external walls ongoing

 

2. CARCASS CONSTRUCTION OF OTHER UNITS IN PROGRESS 

The MEP works on the second block of housing unit to be assembled and casted has reached completion stage while the slab reinforcement has reached completion stage. With this, the block is ready for assembling of the form works and casting which has since commenced.

Three (3) units out of the 5 on this block already has both the ground and first floors already assembled and casted while the ground floor of the 4th floor has also been done and the ground floor reinforcement for the fifth and final unit on this block has also been done in readiness for assembling of formworks and final casting. The activity level on same can be ready at 8%.

 

 
    Assembling of the ground floor
     

  

3. SAND FILLING OF THE SITE CONTINUES

The sand filling of other parts of the project site is still in progress and gradually reaching completion stage.

 
  Continuation of the sand filling process  
     

 

OTHER NEWS

LAGOS STATE GOVERNMENT APPROVES FLYOVER BRIDGE FOR AJAH AXIS AND ABULE EGBA

The Lagos State Government has approved the construction of flyover bridges for two of the State’s high-density traffic areas – the Ajah round about and the Abule-Egba junction. Upon the approval by the State’s Executive Council, the contracts have been duly awarded to contractors for speedy commencement and delivery.

The proposed timeline for the project from start to finish is estimated to be 16 months as stated in a press release issued by Steve Ayorinde, the state’s Commissioner for Information and Strategy on the 13th December, 2015. It was stated therein that the construction of the reinforced concrete flyover and signalized intersection at the Ajah roundabout will be undertaken simultaneously with the rehabilitation of Freedom Road in Lekki with a view to reducing the heavy traffic being recorded at the Ajah round-about and the Lekki-Ikoyi axis. He said the Ajah flyover bridge will have a solar-powered signalized intersection in order to greatly improve traffic while the upgrade on the Freedom road is expected to ease traffic considerably for vehicles using the 3rd roundabout to connect Lekki through Admiralty Way.

While the Ajah project will ease movement of residents and commuters on the Lagos Island - Ibeju Lekki areas, the construction of the reinforced concrete dual-carriage flyover bridge at Abule Egba junction will equally bring joy and relief to millions of commuters that use the Lagos -Abeokuta Expressway in Ifako-Ijaye Local Government Area of the State on a daily basis when completed. Like the Ajah project, Ayorinde said the Abule Egba flyover bridge will also have signalised intersection under it to service Oko-Oba and other link roads within the axis.