Lekki Pearl April Development Update

SITE UPDATE

1. SHOW HOUSE COMPLETED WITH ALL INTERNAL FINISHNG AND FURNISHING DONE

The sample house (Alverstone terrace unit) was completed and put on display for both current

and intending subscribers to view. The unit was fully finished, furnished and fitted to give an

actual feel of the home upon taking full possession – (still open for viewing till date).

Attached are pictures of the interior of the house.

 

 
     
 
     

  

2. CARCASS CONSTRUCTION OF OTHER UNITS IN PROGRESS

2.1 TERRACE UNITS: Other blocks of Terrace units are under construction with few

carcasses of same already standing. The carcass of units C14 to C11 on the same block

as the Show House has been completed and awaiting necessary finishes.

On block C16 to C20, all carcasses have been completed. The excavation of the

foundation trenches is ongoing on block C6 to C10 with the commencement of the

ground beam reinforcement.

  

3 FOUNDATION WORKS COMMENCE ON SEMI – DETACHED UNITS AND BLOCK OF

FLATS

3.1 SEMI-DETACHED UNITS:

3.1.1 Units B1 and B2 – Casting of ground beam completed as well as the slab

with curing of cast slab improving.

3.1.2 Units B3 and B4 - Mechanical plumbing work is completed. Slab

reinforcement arrangement is ongoing, with the level of activity reached

about 65% to completion.

3.1.3 Units B13 and B14 – Casting of ground beam completed as well as the

slab with curing of cast slab improving.

3.1.4 Units B19 and B20 – Slab reinforcement arrangement completed with the

electrical conduit installation ongoing to about 50%. Ground slab

expected to be cast by mid-April.

3.1.5 Units B21 and B22 – Slab reinforcement arrangement completed with the

electrical conduit installation ongoing round slab expected to be cast by

mid-April.

 

3.2 BLOCK OF FLATS:

3.2.1 Block D1 - Ground beam reinforcement arrangement is completed. The

plumbing pipes installation on foundation has been completed with the

electrical conduit installations to be completed by mid-April.

3.2.2 Block D2 - Casting of the ground beam is completed. The mechanical pipe

for ground floor of this block is also complete.

3.2.3 Block D3 - Wall reinforcement arrangement has commenced.


4.0 SAND FILLING OF THE SITE CONTINUES

The sand filling of other parts of the project site is still in progress and gradually reaching

completion stage with attention on the portion that will sit the fully detached houses.